Task Constraint chaning to SNET when adding a new task

K

Kelly O

A user I support reported that each time she adds a new task, it
automatically has a task constraint of SNET. Before the past day or two, the
default constraint was ASAP. Anyone have an idea why this would occur as
soon as a new task is added?

Thanks
 
B

BJ

Go to Tools-Options-Schedule and set it back to "New Tasks Start on Project
Start Date". It's probably set to "New Tasks Start on Current Date".
 
K

Kelly O

Thanks! Our project template was set as you suggested, but somehow the user
must have changed the setting.
 
Top