task custom fields roll up

S

shahab

we have projects with single assignments per task. in PWA 2003, we would do
task updates to custom fields by publishing them as task level fields and
allowing assignments to update them. after updates were 'accepted', when we
opened the mpp file in professional the gantt view would show the updates at
task level (auto roll-up from assignment to task?). But in 2007, whether we
set the custom fields to rolldown or not, when an assignment updates the
task, it shows up under task usage, but doesnt roll-up to task. is there some
way to auto rollup or do i have to VBA it??? thanks.
 
M

Mike Glen

Hi shahab,

Try posting on the microsoft.public.project.server newsgroup (forum).
Please see FAQ Item: 24. Project Newsgroups. FAQs, companion products and
other useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 
Top