Task Decriptions

D

Dan

Why is it when I change a task description and publish
project changes to PWA that the new descriptions are not
reflected in PWA tasks?
 
G

Gary L. Chefetz \(MVP\)

Dan:

Publishing new and changed pushes all information for new tasks and new date
information for existing tasks. To change the name description, you need to
republish the assignment using republish selection from the collaborate
menu.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
 
B

Bill

Where in PWA are you looking for the task changes? Do you
need to refresh the OLAP cube?
 
Top