Hi, All:
I am currently working on an enterprise implementation, and I have been
asked if there is a way to assign tasks at the Resource Manager level and
allow the Resource Managers to delegate their respective tasks to their
reporting resources. I know this is possible to an extent, but Project Pro
tends to complain when I attempt to utilize a given resource to several
hundred percent capacity. I realize that this is by design and in the name of
practicality (and indeed humanity), but is there a way to override Project's
utilization parameters?
Is there a better way to handle this?
I appreciate the help.
I am currently working on an enterprise implementation, and I have been
asked if there is a way to assign tasks at the Resource Manager level and
allow the Resource Managers to delegate their respective tasks to their
reporting resources. I know this is possible to an extent, but Project Pro
tends to complain when I attempt to utilize a given resource to several
hundred percent capacity. I realize that this is by design and in the name of
practicality (and indeed humanity), but is there a way to override Project's
utilization parameters?
Is there a better way to handle this?
I appreciate the help.