task dependencies

T

Tonyjstark

I am using M/S project 2000 and my task dependencies are not shown correctly
on my gantt chart. eg if I enter a task with another being a predecessor with
a finish to start type dependency and it shows the two taks starting in
parrallel or even before the other one has finished.

I am not a beginner to M/S project but have never seen this before. I guess
I have set something within the project which has resulted in this but don't
know where to look.

Any ideas?
 
J

JulieS

Hi Tonyjstark,

Check your calculation settings. Should be automatic -- see
Tools > Options, Calculation tab.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
J

JulieS

Hi Strach,

Thanks for the update and the explanation of what was causing the
error. To clarify for anyone else reading along, when Strach
talks about a non-zero % complete, the issue was that once a task
has even 1% complete marked against it, the task also has an
Actual Start date. Once a task has an Actual Start date, it will
not longer respond to changes in predecessors. By setting the %
complete back to zero, you removed the Actual Start date.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top