T
Tonyjstark
I am using M/S project 2000 and my task dependencies are not shown correctly
on my gantt chart. eg if I enter a task with another being a predecessor with
a finish to start type dependency and it shows the two taks starting in
parrallel or even before the other one has finished.
I am not a beginner to M/S project but have never seen this before. I guess
I have set something within the project which has resulted in this but don't
know where to look.
Any ideas?
on my gantt chart. eg if I enter a task with another being a predecessor with
a finish to start type dependency and it shows the two taks starting in
parrallel or even before the other one has finished.
I am not a beginner to M/S project but have never seen this before. I guess
I have set something within the project which has resulted in this but don't
know where to look.
Any ideas?