Task Duration Changes on SAVE & OPEN in XML format

A

Abhijit

Hi,

We have discovered a strange problem in MSProject after installing SP2

The task duration changes when MPP file is saved as XML and XML file is
reopened. This is causing a havoc.

There is nothing specific about the file. File with even one task shows the
problem.

Any help possible. Can I upload the file somehwere?
 
R

Rod Gill

Hi,

I'm running Project 2007 SP2. I created 7 tasks with durations from 1d to 7d
and linked them. Saved to xml. Closed. Create new project from xml file and
finish date of 7th task was same and all durations same.

What's the minimum you have to do to create problem?

--

Rod Gill
Microsoft MVP for Project - http://www.project-systems.co.nz

Author of the only book on Project VBA, see: http://www.projectvbabook.com




Abhijit said:
Hi,

We have discovered a strange problem in MSProject after installing SP2

The task duration changes when MPP file is saved as XML and XML file is
reopened. This is causing a havoc.

There is nothing specific about the file. File with even one task shows
the
problem.

Any help possible. Can I upload the file somehwere?

__________ Information from ESET Smart Security, version of virus
signature database 5083 (20100503) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 5083 (20100503) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top