task duration is affected after I add a resource

A

Arik Segal

I'm an experienced VB programmer, but I'm new to MS-Project. I don't
know why the task duration changes after I modify the task's
resource-list. The task start time jumps from 08:00 to 13:00 and I
can't understand the reason. At the beginning I thought it has
something to do with calendars, but the resource doesn't use any
special calendar. Can anyone help me?


Thanks in advance
 
J

Jan De Messemaeker

Hi,

Programming VBA on Project whilst not knowing project is as safe as start
taming a lion when you are a specialist on whips but never worked with
beasts...

Better learn a lot about the beast first.
It has many more tricks than just changing the duration.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 
J

Jan De Messemaeker

Thanks, Jack.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top