Hello,
"Another way to think of Duration is the 'window of oppurtunity" during
which the team members work on the task.
We allow an executive 5days to approve a deliverable, but the executive will
only perform 2 hours of actual work on the approval. The Duration of this
task, therefore, is 5 days because this is the "window" during which the
executive perfoms the work"
How can i set this in Project 2007 Professional.
If i change the duration of a task, the amount of work change. If i change
the start date, the finish date move backw or the duration have to change.
How can i set a task during 5 days, only 2 hours work starting on 5 nov
until 9 nov.
Thank you,
Koen
"Another way to think of Duration is the 'window of oppurtunity" during
which the team members work on the task.
We allow an executive 5days to approve a deliverable, but the executive will
only perform 2 hours of actual work on the approval. The Duration of this
task, therefore, is 5 days because this is the "window" during which the
executive perfoms the work"
How can i set this in Project 2007 Professional.
If i change the duration of a task, the amount of work change. If i change
the start date, the finish date move backw or the duration have to change.
How can i set a task during 5 days, only 2 hours work starting on 5 nov
until 9 nov.
Thank you,
Koen