Task enterprise codes and Assignment - Timesheet views. WHY DON'T THEY WORK???

B

bill_murphy

I have created a Task Enterprise Outline code and added it to the
timesheet view(and an assigment view) with the hope of using it as a
filter. I re-puplished every project(90+) BUT the view will not show
any values!!!

They do work in a Project Views????

WHAT IS GOING ON!!!
Help
 
D

Dale Howard [MVP]

Bill --

Did you add the outline code to the list of published fields in each project
using Tools - Customize - Published Fields, and then republish the
assignments using Collaborate - Publish - Republish Assignments? If you
didn't do these steps, the information will not show up in the PWA timesheet
page. You must repeat this process for every project. Hope this helps.
 