Vitek
Hello again in short period,
Can at least Project3 do the following?
------
- PWA/Task View of resource
- he can edit Actual Work done per day and Remaining Work
- also he can edit non-default field Actual Finish
He has done 20 % work (accepted by manager and saved).
Next day he realized the work is completed and so he inserted today
date to the Actual Finish.
------
I expect his manager will accept the change in Actual Finish field.
Then the task will reach 100 %. Only 20 % hours from the planned
amount will be saved on server (e.g. 2h of 10h).
I know with enabling resources to edit Actual Finish I can encounter
with some problems (multiple resources/task...). But firstly it doesnt
function at all!
After accepting by mng, the field Actual Work in PROJECT will not
change.
I dont know why MS permit to insert that field...
I will understand you ll answer me: IT is not possible.
Thank you for answers (potentially I will expand on this issue)
Vitek
Can at least Project3 do the following?
------
- PWA/Task View of resource
- he can edit Actual Work done per day and Remaining Work
- also he can edit non-default field Actual Finish
He has done 20 % work (accepted by manager and saved).
Next day he realized the work is completed and so he inserted today
date to the Actual Finish.
------
I expect his manager will accept the change in Actual Finish field.
Then the task will reach 100 %. Only 20 % hours from the planned
amount will be saved on server (e.g. 2h of 10h).
I know with enabling resources to edit Actual Finish I can encounter
with some problems (multiple resources/task...). But firstly it doesnt
function at all!
After accepting by mng, the field Actual Work in PROJECT will not
change.
I dont know why MS permit to insert that field...
I will understand you ll answer me: IT is not possible.
Thank you for answers (potentially I will expand on this issue)
Vitek