task help

T

tom wilson

I am new to MSP 2003 Standard

Can someone explain how I do the following:-

I have a task that runs over an elapsed time of 6 weeks but the actual work
lasts for
8 non contiguous days.

Its like scheduling a fortnightly meeting over a 6 month period.

Many Thanks In Advance

Tom
 
M

Mike Glen

Hi Tom,

Welcome to this Microsoft Project newsgroup :)

Try Insert/Recurring Task. Fill in the details as best you can and set the
periodicity of the 8 non-consecutive days to the most common - say Weekly,
every Monday and OK. Then click the little + sign next to the Recurring
Task's name to expand the details. Now you can adjust each one to meet your
planned days.

Alternatively, set your task at 6 weeks, assign your resource and then in
the Resource Usage view, amend the work requirements to suit the planned
days.

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top