O
Omega430
I scheduled several projects, assigned resources and have a standard 8 hour
day set up with 1/2 hour for lunch. 7a - 3:30p. When I switched the view to
task usage, it showed all my resources listed as working 7 hours a day. I
want this to reflect 8 hours in a work day. Which setting do I cahange to
make this default? This is more for a billing thing, so I need to know man
hours we are charging for.
Thanks
day set up with 1/2 hour for lunch. 7a - 3:30p. When I switched the view to
task usage, it showed all my resources listed as working 7 hours a day. I
want this to reflect 8 hours in a work day. Which setting do I cahange to
make this default? This is more for a billing thing, so I need to know man
hours we are charging for.
Thanks