Task ID's and Unique ID's

B

Brad

In the SQL file MSP_WEB_ASSIGNMENTS, does anybody know what it means if the
fields "TASK_ID" and "TASK_UID" have "-1" as values?

Many Thanks,
Brad
 
L

Lars Hammarberg

The task was created from PWA using the Create new task option (can't
remember right here and now the exact words on the link) or from a PDS
method call.
This entry will be replaced with a correct entry (having correct ids for
these fields) when the owner of the plan opens/saves and publishes the plan
again.
 