Gary/Dale,
Thanks for the feedback. You guys rule!!
I think answering Gary's question a may answer Dale's.
Let me set the stage more clearly. MSP2K7 and WSS3.0
I have project schedule tasks assigned to team members built from "build
team from enterprise," they all have project tasks assigned, and heve
recieved emails and task list updates from a published project.
My issue is:
I am using the tasklist in sharepoint under a published project's work
space, Tasks, settings, create view, Datasheet View.
Gary says that these tasks do not have anything to do with PWA. That is OK.
That means that these tasks do NOT roll up to the project sschedule, right?
Here is my question: Can the created in sharepoint-Task-Dataview sheet show
up in a team members task list? Can they recieve email notification of the
assignment? Are they available in the DB for reporting or cube analysis? If
so, how do I take the next step?