David

How can I create a task level report on the Portfolio
Analyser. I would like to have the report which shows the
resource & his tasks across all projects in the Portfolio
Analyser. Any ideas would be appreciated?
Regards,
David
 
G

Gary L. Chefetz

David:

You first need to customize the analyzer to contain task-level data, which
it does not contain by default. See documentation on MSDN for Microsoft's
offerings on the subject. Hugues Perron has shared some of his knowledge on
the OLAP cube and has some files available under Project Server Downloads at
http://www.projectserverexperts.com/


--

Gary Chefetz [MVP]
http://www.msprojectexperts.com
"We wrote the book on Project Server"