Task must start at 09:00

B

Benedykt

Hello,

in one project I have a task which must start exactly at 09:00. So,
for instance, if previous task is finished at 10:00, this task must
start at 09:00 next day. (I hope you understand what I mean)
How can I achieve that?
 
M

Mike Glen

Hello,

in one project I have a task which must start exactly at 09:00. So,
for instance, if previous task is finished at 10:00, this task must
start at 09:00 next day. (I hope you understand what I mean)
How can I achieve that?

Hi Benedykt,

Create a new calendar where every working day starts at 0859. Insert a
task before the 0900 task, give it a Duration of 1 minute, make it use
the new Task calendar and link it in. Post back if you need more
details.

FAQs, companion products and other useful Project information can be
seen at this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
B

Benedykt

Create a new calendar where every working day starts at 0859. (...)

Great idea, thanks a lot for it! I thought about using custom columns,
but your solution seems more easy.
 