Hi... Is there a way we can secure the task name once the project in PS 07 is
baselined. We dont want resource's/PM's to change / modify the task names.

Thanks,
Trivikram.
 
J

Jack Dahlgren

Not really. You can detect the change by storing it off into another field,
or try to stop some changes through the use of a macro, but those approaches
can all be easily bypassed.

If you trust these people to manage your projects and people, don't you
trust them with the schedule?

-Jack Dahlgren
 
S

ST

As Jack said, the macros can be bypassed if someone knows how.

I have one such macro for you if you would like to try it.
 
T

Trivikram

Hi ST... Thanks for the help. Sure I would love to try it... please send it
me to this id vichram @ yahoo.com...

thanks,
Trivikram.
 