Why don't task names in the Project Page match the schedule file's task
names, even after "publishing all information"?
Here's the test I did:
1) Created a test schedule, with task ID#2 named "Test Task", assigned
myself to the task (I'm an Enterprise Resource) and published both the
Assignments and the Project Plan with the summary.
2) I updated the task in the web, and accepted the task changes.
3) In MSP, I changed the name of task ID#2 from "Test" to "Test
Tasktttttttttttt"
4) I republished "All Information"
The Task name doesn't change in the "View A Project" view! When I click on
the plan in the "Project Center" view, and the "View A Project" view opens,
Task 2 still says "Test Task", not "Test Tasktttttttttttt".
BTW: The Assignments view correctly displays "Test Tasktttttttttttt" as the
task name.
How do I get the task name to change in the Projects Detail view????
names, even after "publishing all information"?
Here's the test I did:
1) Created a test schedule, with task ID#2 named "Test Task", assigned
myself to the task (I'm an Enterprise Resource) and published both the
Assignments and the Project Plan with the summary.
2) I updated the task in the web, and accepted the task changes.
3) In MSP, I changed the name of task ID#2 from "Test" to "Test
Tasktttttttttttt"
4) I republished "All Information"
The Task name doesn't change in the "View A Project" view! When I click on
the plan in the "Project Center" view, and the "View A Project" view opens,
Task 2 still says "Test Task", not "Test Tasktttttttttttt".
BTW: The Assignments view correctly displays "Test Tasktttttttttttt" as the
task name.
How do I get the task name to change in the Projects Detail view????