Task Notes & Assignment Notes

E

e

I need resources to enter Notes on some tasks, however for reporting purposes
I need the notes to have a link to the resource that entered the note. In
other words my Note needs to be assignment based, not just task based. Any
suggestions on how to go about this? thanks
 
J

JackD

Simply use the assignment Notes field. You can insert and see it when you
are in the task usage or resource usage views.
 
E

e

thanks. I should have stated before that I need the information entered from
PWA. Any other suggestions?
 
Top