We are new to Project2K3.
We have a resource pool of 3 individuals:-
Bill
Bob
Barry
We have three tasks that need to be completed:-
Migration 200 man days Bill to start
Security 60 man days Bob to start
Databases 40 man days Barry to start
one individual is assigned to each task and will then move to migration
when they have completed their task.
All tasks start simultaneously
Migration is made up of 100+ programs which we do not want to set up as
sub-taks as the resource pool will simply pick up the next program
rather than assign specific programs to a resouce member.
how do we set this up so that the gantt chart is automatically updated
as each resource moves onto the main project?
Obiron
We have a resource pool of 3 individuals:-
Bill
Bob
Barry
We have three tasks that need to be completed:-
Migration 200 man days Bill to start
Security 60 man days Bob to start
Databases 40 man days Barry to start
one individual is assigned to each task and will then move to migration
when they have completed their task.
All tasks start simultaneously
Migration is made up of 100+ programs which we do not want to set up as
sub-taks as the resource pool will simply pick up the next program
rather than assign specific programs to a resouce member.
how do we set this up so that the gantt chart is automatically updated
as each resource moves onto the main project?
Obiron