Task Priorities

E

EasySite

Hello,

Need some advice/help please. In PWA, View My Tasks, resources get a list of
their tasks they will/are working on. However the tasks are in no particular
order so how will the resource know which task to work on next?

I want the tasks to be listed with the highest priority first. I know I
could just add a 'Priority' column then order by, but it will mean that I
have to remember what priority I entered for each project so that it will
order in the correct order.

Thnks in advance.
 
M

MAT

Hi...
You can open all of the Enterprise-Projects in Microsoft Project
Profesiional (all at the same time). Then You can change the Priotiäts of all
projects. If you now level any of the project (the others are open), the
tasks of the Project with the high prioritatnummer will begin earlier. So the
ressources can know on which task they sohould work.
I hoe this helps.
MAT.
 
D

Dale Howard [MVP]

EasySite --

The default sorting on the View My Tasks page is by the Start date of each
task. Shouldn't this indicate which task a team member is supposed to work
on next?
 
Top