Hi -

I have two projects (A and B). Project A is a higher
proiorty than Project B.

However, I want a task within Project B (the lower
priority) to be a higher priority than a task in Project
A. These two tasks are assigned to the same resource.

How can this be accomplished without temporarily changing
the priuority of the projects?

Thanks
 
G

Gérard Ducouret

Hello Randy,

The Project level priority has always priority over the Task level priority.
So you'll have to change temporarily the projects priority...or to set
youself a value in the Leveling Delay field (NB : elapsed days)

Gérard Ducouret
 