I have a user with the following scenario. I know for the tool to work as it
is designed, you've got to allocate resources to a task but I'm wondering if
anyone has found, or can think of, a way to accomodate this?
"I have 2 types of tasks in my project plan - 2007 AutoP Series II Support
* Fixed Units with a percentage and work associated to create the duration
* Fixed Duration with 0% and no work just duration.
Type 1 are showing up in the resources 'Current Task' view with no problem,
but the Type 2 tasks are not. How do I get them to show in the 'Current
Task' view without adding a % or hours to them? These are tasks that are
set up just as place holders for time spent that I don't want them to have
time allocated to the resource so that it takes away from their
availability....anyone have any ideas?"
is designed, you've got to allocate resources to a task but I'm wondering if
anyone has found, or can think of, a way to accomodate this?
"I have 2 types of tasks in my project plan - 2007 AutoP Series II Support
* Fixed Units with a percentage and work associated to create the duration
* Fixed Duration with 0% and no work just duration.
Type 1 are showing up in the resources 'Current Task' view with no problem,
but the Type 2 tasks are not. How do I get them to show in the 'Current
Task' view without adding a % or hours to them? These are tasks that are
set up just as place holders for time spent that I don't want them to have
time allocated to the resource so that it takes away from their
availability....anyone have any ideas?"