J
jp
I have a task "TaskQ" which was supposed to start on 8/13/09.
However, it was actually started on 7/16/09 so I updated the field
with that date. The duration of the task was 1.41d. However, somehow
the Actual Finish date goes back to 1.41d after the original start date of
(8/13/09).
Is this correct? I thought if I put in the "Actual Start date" and the
duration (1.41d)
that the MS-Project 2003 would automatically put in "Actual Finish Date" of
7/17/09.
Am I wrong on this one and if so, can you guide me in the best way of
updating this
task.
-jaime
However, it was actually started on 7/16/09 so I updated the field
with that date. The duration of the task was 1.41d. However, somehow
the Actual Finish date goes back to 1.41d after the original start date of
(8/13/09).
Is this correct? I thought if I put in the "Actual Start date" and the
duration (1.41d)
that the MS-Project 2003 would automatically put in "Actual Finish Date" of
7/17/09.
Am I wrong on this one and if so, can you guide me in the best way of
updating this
task.
-jaime