I have zeroed out remaining hours both in the employees (this happens to all
employees, not just a few) timesheet and in the project, have made them
proposed from committed, I have closed the project and the task STILL remains
in their timesheet, PLEASE help!!!!!!!
 
D

Dennis Harvey

In my experience with MSP 2003 w/project server....you have done the right
things. You changed Remaning work to 0, and you changed the Booking Type
from Commited to Proposed. But, did you then re-Publish the plan? It won't
take effect until you do.

This has always taken tasks off timesheets at my site. But be aware, if you
are using the OLAP cube, changing the booking type to proposed will remove
the resources task from the cube.
 