Task tracking in PWA

Z

Zay

After customization of PProf03 for task sheets and adding fileds by
Tools-customize-published fields option and then republishing projects
i am still not able to see the customized columns in PWA. I only see
% of work complete and remaining work option to track the tasks. i
want to allow team members to put the actual hours worked on each task
by using PWA. these actual hours should be indepedent of how much
hours are assigned for the said taks.
can i do this and how? thanks in advance
Zay
 
D

Dale Howard [MVP]

Zay --

From your description, it sounds like your Project Server administrator
needs to modify the Timesheet view in PWA to include the columns you wish
your users to see. In addition, it sounds like your organization is using
the % Work Complete method for tracking progress. If this is the case, your
Project Server administrator may also need to change the default method of
tracking progress to Actual Work and Remaining Work, and then unlock this as
the default method of tracking progress. Hope this helps.
 
Top