Task Type Question

S

Sinister

I can't seem to find a difference between Fixed-Work and Fixed Units. Could
someone explain?
 
J

Jack Dahlgren

There is a fundamental equation in Project

Work = Duration x Units

Fixing work means that if you change the duration of the task, the total
work will remain the same, but the units (% of resource assigned) will
change proportionally. Fixing Units means that duration changes will cause
proportionate changes in work.

-Jack Dahlgren
http://zo-d.com/blog
 
M

Mike Glen

Hi Sinister,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #11 on task types, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top