Hi,
A really strange thing:
Resources are updating their tasks through the PWA using "My Tasks" option
entering hours per day.
After Project Manager accepts the tasks, it shows at the resource usage view
in Project Pro.
The thing is that the resource usage view does not refelcts the correct
updates
(showing 5.23h insted of 5h and 2.82h instead of 2h etc' and dates are off
as well).
The organization is using one standard calendar and i have checked the
server configurations as well.
The application is project server 2007+ SP1.
Please help...
asuchi
A really strange thing:
Resources are updating their tasks through the PWA using "My Tasks" option
entering hours per day.
After Project Manager accepts the tasks, it shows at the resource usage view
in Project Pro.
The thing is that the resource usage view does not refelcts the correct
updates
(showing 5.23h insted of 5h and 2.82h instead of 2h etc' and dates are off
as well).
The organization is using one standard calendar and i have checked the
server configurations as well.
The application is project server 2007+ SP1.
Please help...