D
Darrell
I have a situation where I originally published a project for a PM. Once the
other PM was up-to-date on using the Server w/Project Pro the PM re-published
the schedule and checked the "Become the Manager for these assignmnets" box.
Now when resources update tasks the PM gets some updates and I get other
updates from the same resource instead of all updating going to the new PM.
It is as if I am the owner of some of the tasks and the PM is the owner of
the rest of them. Will the PM re-publishing again resolve this?
other PM was up-to-date on using the Server w/Project Pro the PM re-published
the schedule and checked the "Become the Manager for these assignmnets" box.
Now when resources update tasks the PM gets some updates and I get other
updates from the same resource instead of all updating going to the new PM.
It is as if I am the owner of some of the tasks and the PM is the owner of
the rest of them. Will the PM re-publishing again resolve this?