Task updates in Project Pro 2007

D

Dots

I have upgraded my Project Server 2007 to SP1 and my Project Pro 2007 to SP1.
When users are approving and updating tasks, these task updates are NOT
being respresented in Project Pro. If I go to Rsource usage, I see the
correct hours, but I do not see the % complete being updated. In a
particular case, the % complete should have changed to 100% complete, yet
remained at 0%. Any clue as to why this is happening? I saw this same
behavior prior to the SP1 upgrade. And it still persists following the
upgrade. HELP!
 
M

Marc Soester [MVP]

Hi Dots,

Can you ask your resources to re-submit the task changes and let me know if
you can approve or reject it?

Does this only occur on one project or all?

Thanks
 
D

Dots

HI Marc,
I have had the resources resubmit their tasks and the PM accept. The %
still does not reflect the changes.?
 
M

Marc Soester [MVP]

Hi Dots,

when you say the % complete does not change, I presume that no information
is transfered. Is this correct?

Also, do you have this issue only on one project?

Have you checked the Project Server Queue and event logs of the server and
if so, did you get an error message?
Thanks

--
Marc Soester [MVP]
State Manager: EPM
http://marcsoester.blogspot.com
 