Task View Question

B

Buzz

In the Task View of the PWA, Timesheet view, All or
current tasks being displayed, I need to be able to see
the BASELINE WORK column, os my resources can gauge their
actual time against their budgeted time. Is there any way
to change the PWA display of the timesheet view to include
Baseline Work?

Thanks,
Buzz
 
D

Dale Howard

Buzz --

Open your first published project and do the following:

1. Click Tools - Customize - Published Fields
2. In the dialog box, copy the Baseline Work column from the left side to
the right side
3. Click OK
4. Click Collaborate - Publish - Republish Assignments

Step 4 will "push" the new column to each user's timesheet for that project.
You will need to open each of your published projects and do the same 4
steps on each one. Hope this helps.
 