Task View - Timesheet Missing Remaining Work/Actual Work Columns

J

Jan

I have one resource's (as far as I know) timesheet where the Remaining &
Acutal Work columns do not display. I have checked several other resources
and confirmed that their timesheet does display these two columns. I tried
to expand all the columns in the time sheet to see if the missing columns had
been minimized and found nothing. I've done a search on the specific field
and nothing.

How do I get this resouce to see these two columns in their timesheet?
 
Top