sla837 --
Are you saying you want to split up the task into slices of time? If that
is the case, you will need to create a "split task" using the Split Task
button on the Standard toolbar. To split a task, click the Split Task
indicator then click and hold the mouse button at the point on the task
where you want the first split, and drag the remaining portion to the right.
Release the mouse button when the right-hand split portion begins on the day
desired. Continue the process until the task is split appropriately.
If this is not what you are referring to in your question, please clarify
your question further. Hope this helps.
--
Dale A. Howard
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
sla837 said:
How do I display a task in Project that is the same task but with
different dates. Instead of a continuous line I want to identify the
different dates