P
Pinocchio
I have a task whose only constraint is to happen during the month of August.
In other words, it should not start earlier than 1-Aug, but also shouldn't
finish later than 31-Aug. What is the best way to model such a task in MS
Project? Can I set two flexible constraints on the same task?
Pinocchio
In other words, it should not start earlier than 1-Aug, but also shouldn't
finish later than 31-Aug. What is the best way to model such a task in MS
Project? Can I set two flexible constraints on the same task?
Pinocchio