Can someone explain to me what's the different between these two
fields? I'm currently track some ideas using TASK_ID but another
piece of software is using TASK_WINPORJ_UNIQUE_ID. Which is better to
use?

Thanks,
 
R

Rod Gill

ID is the row number in Project Pro, Unique ID is the Unique ID field in
Project Pro. Whilst the ID value changes when you insert, delete or move
Tasks, the Unique ID does not. Insert the Unique ID column in Project Pro
and experiment. the UID is a much safer field to use with external apps as
it doesn't change.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




Joe Mitchel said:
Can someone explain to me what's the different between these two
fields? I'm currently track some ideas using TASK_ID but another
piece of software is using TASK_WINPORJ_UNIQUE_ID. Which is better to
use?

Thanks,

__________ Information from ESET Smart Security, version of virus
signature database 4468 (20090929) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4468 (20090929) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
J

Joe Mitchel

Where can I find the TASK_WINPORJ_UNIQUE_ID? The Task object in
ProjectDataSet doesn't seem to include it?
 