Tasks assigned by project manager is not visible to the resource

S

Shiva Chaitanya

Hi

We are using project server 2003. Project manager added a new task (only one
task) to resource. After

adding the task project manager have done publish -> New and changed

assignments. Actually, this is the step to assign a new task to an
enterprise

resource. But, the resource was not able to view the task in his timesheet
for that

project only (for remaining projects he was able to see and other project

managers has assigned new tasks to him. And those tasks were visible.

But, for one project the resource was not able to see that task. when I
logged into

project web access as an administrator, selected that resource,

(resources -> adjust actuals) i was also not able to see that task in his
timesheet.

Any suggestions on this would be really appreciated.


Thank you,
Shiva Chaitanya.
 
Top