Lisa H --
There is no way that resources could accidentally become assigned to tasks
in a project, let alone report actuals against them. I suspect your PM did
this accidentally, and doesn't want to fess up to it now. He/she should
immediately remove the resources from the summary tasks and republish the
project. Hope this helps.