Tasks at 100% complete

D

Debbie Stein

There are times where people still need to post time in PWA to tasks that
were previously set to 100% complete. In our set up, they are not able to do
this. Is there a way?
 
D

Dale Howard [MVP]

Debbie --

What do you mean by "in our set up, they are not able to do this"? What is
preventing your team members from entering time against a task that was
already marked as 100% complete?
 
D

Debbie Stein

The task is greyed out in the user's task view, and no time can be posted
against it.
 
D

Dale Howard [MVP]

Debbie --

What part of it is grayed out in PWA? Are Actual Work and Remaining Work?
Are % Work Complete and Actual Work? Are Remaining Work in the task sheet
and Actual Work in the timephased grid on the right? Let us know.
 
D

Debbie Stein

Remaining work in the task sheet and Actual work in the timephased grid on
the right.
 
D

Dale Howard [MVP]

Debbie --

Are you using Managed Time Periods with Project Server 2003?
 
D

Dale Howard [MVP]

Debbie --

Is ANY cell unlocked for editing anywhere on the completed task?
 
D

Dale Howard [MVP]

Debbie --

It suddenly just occurred to me, is the task in question a cancelled task,
by chance? Does it have a black X in the Indicators column? Let me know.
Otherwise, I'm totally puzzled by the behavior your are describing.
 