T
Ti Jefferson
We are experiencing an issue where tasks assigned to
individuals are not being displayed to the User in PWA.
Here's the steps we are doing. (We are using Project/PWA
2002)
1. Publish the initial plan using Collaborate|Publish|All
Information
2. Updating the plan with specific resource assignements
and additional tasks. Then using Collaborate|Publish|New
and Changed Assignments. The tasks and assignments are
remaining in the Plan and are displaying within the
Project View of PWA. Howevever, within the Task view for
the User assigned the tasks - they do NOT see the new
tasks. Obviously, this causes a problem for the Users in
updating their tasks if they can't see them.
Any ideas/suggestions on how to correct this, or what we
are doing incorrect would be appreciated.
Thanks!
individuals are not being displayed to the User in PWA.
Here's the steps we are doing. (We are using Project/PWA
2002)
1. Publish the initial plan using Collaborate|Publish|All
Information
2. Updating the plan with specific resource assignements
and additional tasks. Then using Collaborate|Publish|New
and Changed Assignments. The tasks and assignments are
remaining in the Plan and are displaying within the
Project View of PWA. Howevever, within the Task view for
the User assigned the tasks - they do NOT see the new
tasks. Obviously, this causes a problem for the Users in
updating their tasks if they can't see them.
Any ideas/suggestions on how to correct this, or what we
are doing incorrect would be appreciated.
Thanks!