Tasks being Dropped in PWA

T

Ti Jefferson

We are experiencing an issue where tasks assigned to
individuals are not being displayed to the User in PWA.
Here's the steps we are doing. (We are using Project/PWA
2002)

1. Publish the initial plan using Collaborate|Publish|All
Information

2. Updating the plan with specific resource assignements
and additional tasks. Then using Collaborate|Publish|New
and Changed Assignments. The tasks and assignments are
remaining in the Plan and are displaying within the
Project View of PWA. Howevever, within the Task view for
the User assigned the tasks - they do NOT see the new
tasks. Obviously, this causes a problem for the Users in
updating their tasks if they can't see them.

Any ideas/suggestions on how to correct this, or what we
are doing incorrect would be appreciated.

Thanks!
 
D

Dale Howard [MVP]

Ti --

Do your team members have the "Current tasks" option selected in the
sidepane on the left side of the View My Tasks page? If so, and if the
newly published tasks are more than 10 days in the future, they will not
qualify as current tasks and will be hidden from view. If this is the case,
ask your team membes to click the "All tasks" link in the sidepane to make
sure all of the tasks are there. Hope this helps.
 
Top