Tasks - Can not locate the fields in which the recurrence informationis kept?

J

Jim5941

I went to a table view for my tasks,
went to the Field Chooser and chose "All Task Fields"
I wanted to select the fields related to the recurrence of tasks...
I "assumed" they would be similar to the calendar fields/functions:
Recurrence range start & end dates, recurrence pattern, etc...

but... I can not find any fields to add to my table view to display
the information of this sort...
I have repeating tasks, is there a way to display the information
related to how they "repeat"?

Sorry if I am missing something silly, I had no problems setting this
view up for my calendar appts.
 
S

Sue Mosher [MVP]

You're not finding anything, because there is nothing to find. The recurrence
pattern information is not stored in simple fields that can be displayed in a
view.
The only thing you can do is distinguish recurring tasks from those that
are not recurring by grouping on the Is Recurring field.
 
J

Jim5941

You're not finding anything, because there is nothing to find. The recurrence
pattern information is not stored in simple fields that can be displayed in a
view.  
 The only thing you can do is distinguish recurring tasks from those that
are not recurring by grouping on the Is Recurring field.
--
Sue Mosher, Outlook MVP
   Author of Microsoft Outlook 2007 Programming:
     Jumpstart for Power Users and Administrators
   http://www.outlookcode.com/article.aspx?id=54

Dang ...
It sure does seem odd that Microsoft would not allow users to view
their data with that kind of that granularity ....

BUT ... I thank the messenger ;-)
Thanks for taking the time to share your knowledge Sue!

Jim
 