P
PRibeiro
I have a project now that the total of tasks' duration is different from
the total project duration.
The reaosn is that during the project, my client will use the
facilities and we will not be able to work during that period. I would
like to show to the client that our "real" work duration is much less
than the actual project duration, but in the summary tasks it will sum
up all the project duration from the day it starts until it ends. My
working calendar is 7 days/week, 8hours /day
Is there any way to show both durations (sum up of the tasks duration's
and calendar duration)?
the total project duration.
The reaosn is that during the project, my client will use the
facilities and we will not be able to work during that period. I would
like to show to the client that our "real" work duration is much less
than the actual project duration, but in the summary tasks it will sum
up all the project duration from the day it starts until it ends. My
working calendar is 7 days/week, 8hours /day
Is there any way to show both durations (sum up of the tasks duration's
and calendar duration)?