My project plan is showing a number of tasks finishing in the middle of the
day. For example a task that starts on Fri 03/12/04 at 09:00 with a 22 day
duration is finishing on Fri 07/01/05 at 11:00. Why does it not finish at
the end of the day?
Any ideas?
Thanks in advance
Sally