Tasks finishing in the middle of the day

S

Sally

Hi there
My project plan is showing a number of tasks finishing in the middle of the
day. For example a task that starts on Fri 03/12/04 at 09:00 with a 22 day
duration is finishing on Fri 07/01/05 at 11:00. Why does it not finish at
the end of the day?

Any ideas?

Thanks in advance
Sally
 
D

Dale Howard [MVP]

Sally --

Microsoft Project determines the Finish date and time of any task according
to the Start date and time and the calendars of the resources assigned to
the task. Whenever you see what looks like "weird" scheduling, you should
always examine the calendars of the resources assigned to the task. Hope
this helps.
 