Tasks linked to Master

N

Nir

Hi,
I have sub-projected inserted in a Master plan.
Tasks are linked from the subs to tasks in the master.
2 questions
A. I would like not to see the Gray lines (tasks from the master) in the
subplans

B. I would like to block access from the subs to the master.

thanks
 
J

John

Nir said:
Hi,
I have sub-projected inserted in a Master plan.
Tasks are linked from the subs to tasks in the master.
2 questions
A. I would like not to see the Gray lines (tasks from the master) in the
subplans

B. I would like to block access from the subs to the master.

thanks

Mir,
Whether or not the external "ghost" tasks show up is controlled by
Tools/Options/View tab. Uncheck the "show external
predecessors/successors".

What exactly do you mean by "...block access from the subs to the
master."?

John
Project MVP
 