tasks order

J

jackie

Hello

I have a bunch of tasks within an ms project file that needs to be ordered
by finish date. What is the best way to achieve this?

Many thanks
J
 
G

Gérard Ducouret

Jackie,

Have you tried the following:
Project / Sort / By Finish Date.
NB: you can hide the Summry tasks with a filter like:
Project / Filtered for / More filters / New...
Field Name : Summary
Test : equals
Value : No

Gérard Ducouret
 