Hello everyone,

I am having an 'intermittent issue' where tasks for some projects are
visible on the Project - Task Detail view but are not visible on the
timesheet view. This is an intermittent issue because it will occur
for a resource on some of her projects but not on others.

Here is what I have checked:
The resource is an Enterprise resource on the Project Plan.
The resource is 'Committed' on the Project Plan
We are viewing all tasks on the timesheet
There don't appear to be any issues with the Published Project

Any other trouble shooting steps I should take?

Please advise.
 
J

Joe

As a first step, try a "re-publish" on the task that are not showing up and
see if they appear. This will eliminate the possibility that they were
"hidden" from the timesheets.
 
L

Laureen

One other area you can check is the task usage view and make sure that there
is enough "work" allocated. If the task is completed (there are zero hours
for remaining work) it might not show up on the timesheet.
 