Teams - My Tasks - Verifying how this is suppose to work

T

TroyS

I've set up a project schedule where the tasks are business unit buckets.
I've setup Teams and have assigned named resources to teams.
I've then assigned Teams to the Business Unit Tasks and have published.

As a PWA Admin, I've placed myself in one Team where typical Team Names
might be Engineering, Technical Services, etc.

When i go to My Tasks, i see separate line items for each Task/Team
combination. For example, on Business Unit task is Project Office. In My
Tasks, i see the Project Office Task yet i see it repeated for each Team Name.

I would have expected that i only see the Task Name with only the Team Name
that i belong to....not the same task name repeated mutliple times and with
Team Names in the Resource Name field that i don't even belong to...

Please advise as there are a number of Business Unit Tasks and i have now 6
pages of My Tasks from this one project.
 
Top