"This resource should be leveled based on a day by day setting".

K

ks2008

"This resource should be leveled based on a day by day setting".
Could explain, what it means ?
thanks
KS
 
D

Dale Howard [MVP]

KS --

That message means that the resource is assigned to more than 8 hours in one
or more days on one or more tasks in the project, such as when the resource
is assigned to 16 hours of Work in a single day time period. Hope this
helps.
 
M

Mike Glen

Hi KS,

To add a bit, you probably got this message when levelling. In the
Levelling dialog, select "Look for overallocation on a" ... select day by
day.

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top