Time on Project

G

Guest

Times of ressource on a project are moved on an other
period or are deleted when I changed the finish date of
this project !!!

Somebody can help me please ?
Thanks
 
G

Gary L. Chefetz [MVP]

You need to ask yourself what you're doing when you change the finish date.
If you've got tasks that get moved as a result of your change, their actual
work values will move with them. You also need to be very familiar with the
behaviors of Project in distributing work across certain task types such as
fixed duration tasks, and structure you plan according to the end result you
desire.

If you care to give very specific examples of what you're seeing and doing,
perhaps we can explain the behavior you're observing.
 
Top