Vincent
Hi, I received a strange question as follows,
A project manager completed project plan and published
into server. He found there is a timestamp beside start
and finish date which is unexplainable. For example,
In project 2002 professional,
Task1 16/02/2004 20/02/2004 4days
However in PWA, it will become,
Task1 16/02/2004 5:00PM 20/02/2004 5:00PM 4 days
We do not know how it will create and can I adjust
manually? Thanks