time remaining reappearing

J

James from Sage

Some users of Project Server 2003 are sometimes finding their time remaining
reappearing later after having zeroed it out and Saving or clicking Update
All.

I haven't been able to reproduce this problem on my home.

Any thoughts?
 
J

Jonathan Sofer

This could be due to the PM not accepting the updates and re-publishing or
adding more work to the task and re-publishing.

Could this be the case in your environment?
 
J

James from Sage

Thanks for the response!

I don't think this is the case here. For some instances, it was the
manager's own tasks and only I publish for these files.

- James
 
Top